New game
Download
Get Academic Plan
Share game
Integrate it into your platform

You can integrate the game into an LMS compatible with LTI 1.1 or LTI 1.3 such as Canvas, Moodle, or Blackboard. This way, the scores will be automatically saved into the platform’s gradebook.
Download
You have exceeded the maximum number of games you can integrate into Google Classroom with your current Plan.

To integrate as many games as you want in Google Classroom, you need an Academic Plan or a Commercial Plan.

You have exceeded the maximum number of games you can integrate into Microsoft Teams with your current Plan.

To integrate as many games as you want in Microsoft Teams, you need an Academic Plan or a Commercial Plan.

Downloading games is an exclusive feature for users with an Academic Plan or a Commercial Plan.

Get your Academic Plan or your Commercial Plan now and start integrating your games into your LMS, website or blog.

If you wish, you can download a demo game here and test its integration:

S2 _MHT_Tu Motor Lean:Elimina desperdicios, Activa flujo

Froggy Jumps

Played 2

About this activity

Lean Construction y Last Planner

Created by

Peru

Download the paper version to play

Make your own free game from our game creator
Compete against your friends to see who gets the best score in this game

Top Games

%
Anonymous
Anonymous
%
%
%
You have exceeded the maximum number of games you can print with your current Plan.

To print as many games as you want, you need an Academic Plan or a Commercial Plan.

Print your game
S2 _MHT_Tu Motor Lean:Elimina desperdicios, Activa flujo
 

Froggy Jumps

S2 _MHT_Tu Motor Lean:Elimina desperdicios, Activa flujoOnline version

Lean Construction y Last Planner

by Keimer Vilcahuaman Carbajal
1

¿Cuál de los siguientes es uno de los 7 desperdicios (muda) en Lean Construction?

2

El sistema Last Planner® se caracteriza principalmente por

3

¿Qué significa PPC en el sistema Last Planner®?

4

Pull Planning es una técnica que planifica las actividades:

5

En una obra en Huancayo, programar actividades interiores durante la temporada de lluvias (diciembre-marzo) es una estrategia Lean para eliminar el desperdicio de:

6

¿Cuál de los siguientes NO es uno de los 5 principios de Lean Construction?

7

En el sistema Last Planner®, el nivel "Lookahead" tiene una duración típica de:

8

El desperdicio "Retrabajos" en construcción se refiere a:

9

En Pull Planning, cuando se pregunta "¿Qué necesitas para comenzar?", el objetivo es:

10

Un PPC de 54% en un proyecto indica que: