New game
Download
Get Academic Plan
Share game
Integrate it into your platform

You can integrate the game into an LMS compatible with LTI 1.1 or LTI 1.3 such as Canvas, Moodle, or Blackboard. This way, the scores will be automatically saved into the platform’s gradebook.
Download
You have exceeded the maximum number of games you can integrate into Google Classroom with your current Plan.

To integrate as many games as you want in Google Classroom, you need an Academic Plan or a Commercial Plan.

You have exceeded the maximum number of games you can integrate into Microsoft Teams with your current Plan.

To integrate as many games as you want in Microsoft Teams, you need an Academic Plan or a Commercial Plan.

Downloading games is an exclusive feature for users with an Academic Plan or a Commercial Plan.

Get your Academic Plan or your Commercial Plan now and start integrating your games into your LMS, website or blog.

If you wish, you can download a demo game here and test its integration:

Proyecto y Rutas: Verdadero o Falso

Yes or No

Played 0

About this activity

Descubre conceptos clave de rutas y CPM/PERT.

Created by

Mexico

Download the paper version to play

Make your own free game from our game creator
Compete against your friends to see who gets the best score in this game

Top Games

%
Anonymous
Anonymous
%
%
%
You have exceeded the maximum number of games you can print with your current Plan.

To print as many games as you want, you need an Academic Plan or a Commercial Plan.

Print your game
Proyecto y Rutas: Verdadero o Falso
 

Proyecto y Rutas: Verdadero o FalsoOnline version

Descubre conceptos clave de rutas y CPM/PERT.

by CESAR URIEL ORTIZ MATEO
1

Algoritmo de Dijkstra funciona con pesos no negativos para encontrar rutas cortas.

2

La ruta crítica es siempre la ruta más corta entre inicio y final.

3

El algoritmo Bellman-Ford puede manejar grafos con pesos negativos.

4

Dijkstra funciona correctamente con grafos con pesos negativos sin modificaciones.

5

PERT y CPM son técnicas para planificar y controlar proyectos mediante diagramas de red.

6

En CPM, las rutas críticas determinan la duración total mínima del proyecto.

7

PERT y CPM no requieren diagramas de red para su aplicación.

8

En CPM, el camino crítico nunca cambia incluso si se retrasan actividades críticas.

9

El problema de la ruta más corta busca minimizar la distancia o el costo entre dos nodos.

10

En PERT, todas las estimaciones de duración son determinísticas.