New game
Download
Get Academic Plan
Share game
Froggy Jumps
Froggy Jumps

EVALUACIÓN DE PROCESO

Integrate it into your platform

You can integrate the game into an LMS compatible with LTI 1.1 or LTI 1.3 such as Canvas, Moodle, or Blackboard. This way, the scores will be automatically saved into the platform’s gradebook.
Download
You have exceeded the maximum number of games you can integrate into Google Classroom with your current Plan.

To integrate as many games as you want in Google Classroom, you need an Academic Plan or a Commercial Plan.

You have exceeded the maximum number of games you can integrate into Microsoft Teams with your current Plan.

To integrate as many games as you want in Microsoft Teams, you need an Academic Plan or a Commercial Plan.

Downloading games is an exclusive feature for users with an Academic Plan or a Commercial Plan.

Get your Academic Plan or your Commercial Plan now and start integrating your games into your LMS, website or blog.

If you wish, you can download a demo game here and test its integration:

EVALUACIÓN DE PROCESO

Froggy Jumps

Played 57

About this activity

La evaluación de proceso es una herramienta continua que verifica el desarrollo de actividades según lo planificado, monitoreando avances, cronogramas, indicadores y recursos para facilitar decisiones oportunas.

Created by

Colombia

Download the paper version to play

Make your own free game from our game creator
Compete against your friends to see who gets the best score in this game

Top Games

%
Anonymous
Anonymous
%
%
%
You have exceeded the maximum number of games you can print with your current Plan.

To print as many games as you want, you need an Academic Plan or a Commercial Plan.

Print your game
EVALUACIÓN DE PROCESO
 

Froggy Jumps

EVALUACIÓN DE PROCESOOnline version

La evaluación de proceso es una herramienta continua que verifica el desarrollo de actividades según lo planificado, monitoreando avances, cronogramas, indicadores y recursos para facilitar decisiones oportunas.

by Leidy dayan rodriguez macias
1

¿Cuál es el objetivo principal de la Evaluación de Proceso?

2

¿En qué fases del ciclo de vida del proyecto se realiza principalmente la Evaluación de Proceso?

3

¿Qué miden los indicadores de insumo?

4

En el método de Valor Ganado (EVM), ¿qué representa el Valor Planificado (PV)?

5

Si la Varianza del Cronograma (SV = EV - PV) es negativa, significa que:

6

¿Cuál es la fórmula correcta para calcular la Varianza del Costo (CV)?

7

¿Qué tipo de acción busca llevar el desempeño futuro del proyecto de vuelta al plan original?

8

¿Cuál es la función principal de un Tablero de Rendimiento (Dashboard)?

9

En el caso práctico de la aplicación móvil, si EV = $40,000, PV = $50,000 y AC = $55,000, ¿cuál es la Varianza del Costo (CV)?

10

¿Cuál de las siguientes NO es una categoría de recursos que debe controlarse durante la ejecución?