New game
Download
Get Academic Plan
Share game
Integrate it into your platform

You can integrate the game into an LMS compatible with LTI 1.1 or LTI 1.3 such as Canvas, Moodle, or Blackboard. This way, the scores will be automatically saved into the platform’s gradebook.
Download
You have exceeded the maximum number of games you can integrate into Google Classroom with your current Plan.

To integrate as many games as you want in Google Classroom, you need an Academic Plan or a Commercial Plan.

You have exceeded the maximum number of games you can integrate into Microsoft Teams with your current Plan.

To integrate as many games as you want in Microsoft Teams, you need an Academic Plan or a Commercial Plan.

Downloading games is an exclusive feature for users with an Academic Plan or a Commercial Plan.

Get your Academic Plan or your Commercial Plan now and start integrating your games into your LMS, website or blog.

If you wish, you can download a demo game here and test its integration:

Construction and Management, Decision Making and Pre-Construction

Froggy Jumps

Played 193 %Accuracy 63 Average time 02:07

About this activity

Examples scenarios in Construction Management

Created by

Philippines

Download the paper version to play

Make your own free game from our game creator
Compete against your friends to see who gets the best score in this game

Top Games

%
Anonymous
Anonymous
%
%
%
You have exceeded the maximum number of games you can print with your current Plan.

To print as many games as you want, you need an Academic Plan or a Commercial Plan.

Print your game
Construction and Management, Decision Making and Pre-Construction
 

Froggy Jumps

Construction and Management, Decision Making and Pre-ConstructionOnline version

Examples scenarios in Construction Management

by Elmaflor Laurejas
1

For a new school project, the PM balances structure and team input. An engineer proposes a safety upgrade with minor extra cost; the manager calls a team meeting instead of deciding alone. Which principle and approach are demonstrated?

2

Scenario: During a typhoon warning, the PM issues direct orders immediately; after the storm, they explain decisions and seek feedback.

3

Scenario: After two failed concrete tests, the contractor follows a full step-by-step review, analyzes causes, and consults technicians before deciding.

4

Scenario: Rushing to pick a subcontractor, the leader relies on first impressions, ignores safety concerns, and refuses to review the choice despite delays. This is an example of:

5

Scenario: For a 4‑story building, the PM involves key field staff early in plan reviews, splits work into clear phases, and assigns responsibilities. Which pre‑planning practice is this?

6

Scenario: You are preparing site requirements for a government infrastructure project. Which set of items falls entirely under pre-construction site setup activities?

7

Scenario: A client asks for a simple scheduling tool to show when each phase of construction will start and finish, plus overall progress to date. They do not need to see how delays in one task will affect others. Which tool should you use?

8

Scenario: A construction company allocates a fixed amount for fuel and small tools at the start of the year, but sets aside a separate flexible fund for emergency equipment repairs and material price spikes. This practice is part of:

9

A rural road project manager takes these steps: 1) sets clear roles; 2) checks design feasibility; 3) resolves drainage issues step‑by‑step; 4) uses a bar chart for timelines. Which set of practices matches the sequence?