Sap PP(169-219): preguntas compradas

Quiz

(1)
Certificación SAP PP

Download the paper version to play

Recommended age: 16 years old
22 times made

Created by

Spain
This game is a version of

Top 10 results

  1. 1
    37:45
    time
    74
    score
  2. 2
    37:28
    time
    69
    score
Do you want to stay in the Top 10 of this game? to identify yourself.
Make your own free game from our game creator
Compete against your friends to see who gets the best score in this game

Top Games

  1. time
    score
  1. time
    score
time
score
time
score
 
game-icon

Sap PP(169-219): preguntas compradasOnline version

Certificación SAP PP

by Manu
1

For which categories can you define BOMs in SAP S/4HANA? (2 correct)

Choose one or more answers

2

How can you set up the supply source for the Kanban process in SAP S/4HANA? (3 correct)

Choose one or more answers

3

What are the consequences if the Dispatched operation status is set for a production order operation?

4

You set up a material as a phantom assembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material (BOM)?

5

Your project used process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?

6

In the Schedule Production app which setting can you make for the planning strategy? (3 correct)

Choose one or more answers

7

Where do you maintain the work center that represents the production line for repetitive manufacturing? (2 correct)

Choose one or more answers

8

Which SAP application can be used for forecasting in Supply Chain Planning? (2 correct)

Choose one or more answers

9

When can the automatic material availability check occur in a production order? (2 correct)

Choose one or more answers

10

Which methods are available for goods issue posting of material components for process orders? (2 correct)

Choose one or more answers

11

In the Capacity Scheduling Table, which settings can you select for the planning strategy? (3 correct)

Choose one or more answers

12

Where do you maintain data to determine the duration of an operation for production? (2 correct)

Choose one or more answers

13

Which business processes are affected by setting in the order type-dependent parameters? (2 correct)

Choose one or more answers

14

What does the material type influence? (2 correct)

Choose one or more answers

15

You want to insert an operation at a certain time on work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?

16

Which standard item categories can you select inside a bill of material (BOM)? (2 correct)

Choose one or more answers

17

You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage. What must you do? (2 correct)

Choose one or more answers

18

Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements? (2 correct)

Choose one or more answers

19

What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?

20

What does forecasting in demand planning cycle include? (3 correct)

Choose one or more answers

21

You want to set up a make-to-order planning scenario for finished material. The bill of material contains two components: one should be procured for each sales order individually, the other one should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which setting do you make to achieve this?

22

You want to use capacity availability checks for production orders. Which settings have to be made for this? (2 correct)

Choose one or more answers

23

What is a work center hierarchy in planning in SAP S/4HANA?

24

Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing? (3 correct)

Choose one or more answers

25

Which information is required when you created a production master in SAP S/4HANA? (2 correct)

Choose one or more answers

26

Which of the following questions do you have to answer before you start creating a BOM? (2 correct)

Choose one or more answers

27

What type of time element can be reduced by strategy settings while dispatching? (2 correct)

Choose one or more answers

28

Which item statuses can you select inside a material BOM? (2 correct)

Choose one or more answers

29

Your quality department detects a deviation in a raw material batch. Unfortunately, this batch has already been used in production. How can you identify all affected finished goods stocks?

30

Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?

31

Your project team decides to use a make-to-order planning strategy for a strategic material in discrete manufacturing. What is the impact of this decision? (3 Correct)

Choose one or more answers

32

Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (P"/OS)?

33

Your customer wants to include restricted-use stock as a potential receipt in the existing ATP check for component availability. Which information is required to implement this change request in the scope of check? (2 Correct)

Choose one or more answers

34

Your customer is using storage location is in SAP ECC and wants to switch to SAP S/4HANA. What do you have to consider?

35

Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?

36

Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? (2 Correct)

Choose one or more answers

37

You want to use finite scheduling. Which conditions must you meet? (3 Correct)

Choose one or more answers

38

You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?

39

You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?

40

You want to schedule an order in the graphical planning board. What are valid planning directions? (2 Correct)

Choose one or more answers

41

You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?

42

You want to represent setup time as a graphical object in the Detailed Scheduling Planning Board. Which actions are needed? (2 Correct)

Choose one or more answers

43

You want to reduce planning efforts for B/C materials. Which planning procedure do you recommend?

44

You want to perform capacity availability checks on your production orders. What must be set for this to occur? (2 Correct)

Choose one or more answers

45

You want to integrate an existing planned order into Advanced Production Planning. Which report do you use?

46

You want to insert an operation at a certain t me on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?

47

You want to create a production order from a planned order. What methods could you use? (2 Correct)

Choose one or more answers

48

You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?

49

You produce your material based on a forecast derived from historical sales and expect it to be in inventory when your customer orders. If customers order more that the forecasted quantity, you want to increase production to try to meet the extra demand. Which is the appropriate planning strategy to use?

50

You need to model goods receipt processing time in Detailed Scheduling. Which modelling options do you have? (2 Correct)

Choose one or more answers