New game
Download
Get Academic Plan
Share game
Integrate it into your platform

You can integrate the game into an LMS compatible with LTI 1.1 or LTI 1.3 such as Canvas, Moodle, or Blackboard. This way, the scores will be automatically saved into the platform’s gradebook.
Download
You have exceeded the maximum number of games you can integrate into Google Classroom with your current Plan.

To integrate as many games as you want in Google Classroom, you need an Academic Plan or a Commercial Plan.

You have exceeded the maximum number of games you can integrate into Microsoft Teams with your current Plan.

To integrate as many games as you want in Microsoft Teams, you need an Academic Plan or a Commercial Plan.

Downloading games is an exclusive feature for users with an Academic Plan or a Commercial Plan.

Get your Academic Plan or your Commercial Plan now and start integrating your games into your LMS, website or blog.

If you wish, you can download a demo game here and test its integration:

Quiz #2: PCS2 Chapter 1-8

Quiz

Played 157 %Accuracy 58 Average time 06:46

About this activity

This 12-minute quiz covers PCS2 Advanced Construction Methods & Equipment Chapters 1–4, based on course materials, RA 9184, PD 1594, and Fajardo’s Construction Management. Read each scenario carefully and select only the best answer per item. Good luck, God bless and enjoy.

Created by

Philippines

Download the paper version to play

Make your own free game from our game creator
Compete against your friends to see who gets the best score in this game

Top Games

%
Anonymous
Anonymous
%
%
%
You have exceeded the maximum number of games you can print with your current Plan.

To print as many games as you want, you need an Academic Plan or a Commercial Plan.

Print your game
Quiz #2: PCS2 Chapter 1-8
 

Quiz #2: PCS2 Chapter 1-8Online version

This 12-minute quiz covers PCS2 Advanced Construction Methods & Equipment Chapters 1–4, based on course materials, RA 9184, PD 1594, and Fajardo’s Construction Management. Read each scenario carefully and select only the best answer per item. Good luck, God bless and enjoy.

by Elmaflor Laurejas
1

You are managing a new government-funded school building project under RA 9184 and PD 1594. The project uses standard construction methods with predictable task durations, so you plan to use CPM for scheduling. Before drawing the network diagram, you first confirm project goals, review site feasibility, list all required tasks, and clarify reporting lines between engineers, contractors, and auditors. Which sequence of processes are you following?

2

Your team proposes two changes to speed up the project: 1. Shorten the roofing task, which has 6 days of float ​ 2. Shorten the foundation pouring task, which is on the critical path You follow the 7-step decision process to analyze both options, then select only the second option. Which two concepts guided your choice?

3

A sudden supply delay puts your project 5 days behind schedule, and you need to meet the government deadline. You call the team, explain the situation clearly, listen to their suggestions for adjustments, then decide to add overtime to the critical path task with the lowest extra cost. Which combination of actions does this demonstrate?

4

Your project has a total duration of 40 days. Task X is on the critical path; Task Y has 7 days of free float. Which action follows proper management and scheduling rules?

5

A construction project for a rural school requires tight coordination between engineers, local workers, and government auditors. The project manager needs to set up a team structure that avoids confusion, clarifies who reports to whom, and prevents one supervisor from managing 18 people directly. Which key principle of organization & management should the manager prioritize?

6

An emergency structural failure occurs at an active construction site, requiring immediate evacuation and quick repairs to prevent accidents. Which leadership style is MOST appropriate for the project manager to use in this situation?

7

A project manager notices that material costs are rising faster than planned. Instead of jumping straight to cutting worker wages, they follow the 7-step decision process: first confirm the exact cause of the cost increase, set targets for acceptable spending, list possible solutions, analyze each option, pick the best one, apply it, and check results over time. At which step does the manager first define what they need to achieve?

8

Your team proposes a plan to speed up building works, claiming it is "100% risk-free" based only on past similar projects, and refuses to consider alternative approaches. What common decision-making pitfall is this team showing?

9

Before starting a new government infrastructure project, which of the following is NOT a required pre-construction activity?

10

You are managing a government-funded road project under RA 9184. A dispute arises between your technical team and the finance team over budget allocations. You gather input from both sides, ensure all instructions are written clearly, and make sure the final decision balances cost limits and safety standards. Which combination of management approaches are you applying?

Feedback

Explanation: First you set up roles and coordination (Organization, Chapter 1), then verify feasibility and break down work (Pre-Planning, Chapter 3), before applying the CPM network method (Chapter 4).

Explanation: You used the structured 7-step decision process (Chapter 2), and correctly applied the rule that only shortening critical path tasks reduces total project duration—non-critical tasks with float do not affect the finish date (Chapter 4).

Explanation: Consulting the team before deciding reflects democratic leadership (Chapter 1). Shortening only the lowest-cost critical path task is the correct application of project crashing (Chapter 4).

Explanation: Task Y has float, so it can be delayed or reallocated without affecting the project. Task X is critical—any delay extends the project finish date, and shortening non-critical tasks does not reduce total time (Chapters 1 & 4).

Explanation: Limited span of control means restricting the number of subordinates one manager oversees to ensure effective supervision. Humanistic Management focuses on people-first values, autocratic leadership is a decision-making style, and standardization is part of Scientific Management, none directly address the number of staff per supervisor.

Explanation: As noted in the material, autocratic leadership is best suited for emergencies that need fast, decisive action. Democratic and consultative styles waste critical time, while laissez-faire provides no direction for urgent safety issues.

Explanation: The 7-step process follows: Identify problem → Set objectives → Develop alternatives → Analyze → Select → Implement → Monitor. Setting objectives comes right after confirming the problem, to define clear goals for the decision.

Explanation: Overconfidence and confirmation bias happen when teams overestimate their own judgment, ignore new risks, and dismiss other options—this matches the scenario described.

Explanation: PERT/CPM and cost crashing are covered in later chapters and done after basic pre-planning. Pre-construction activities include permits, manpower estimates, site setup, and plan feasibility checks.

Explanation: Consulting both teams and valuing their input reflects Humanistic Management; resolving cross-team disputes and clarifying roles follows the principle of functional alignment.